Milestones
Project milestones across the EMSO EVOLVE work packages.
| Milestone | Name | Related WP | Due (month) | Means of verification |
|---|---|---|---|---|
| MS1.1 | Project KO Meeting (MS1.1, T2.1) | WP1 | M2 | Minutes of the meeting |
| MS3.1 | Industry liaison committee ToR (MS3.1, T3.2) | WP3 / T3.2 | M6 | New and updated ToR to share with private sector partners. |
| MS2.1 | First Meeting on landscape analysis with the representatives national communities, (MS2.1, T2.2) | WP2 | M6 | Meeting Report |
| MS2.3 | Questionnaire to representatives of national contexts for OOS (MS2.3, T2.3) | WP2 | M8 | Questionnaire implemented and running |
| MS3.2 | Private sector stakeholder requirements engagement (T3.2) | WP3 / T3.2 | M12 | A list of identified private sector needs and expectations relevant to EMSO ERIC services. |
| MS2.7 | Membership engagement roadmap (V1) (MS2.7, T2.5) | WP2 | M12 | Report published |
| MS4.1 | EMSO Observation Capacity Review Completed (T4.2) | WP4 | M14 | Deliverable D4.1 approved and shared with WP2, WP5 |
| MS7.1 | CED plan update (BLIT) (T7.2) | WP7 | M18 | Updated CED Plan Document |
| MS6.2 | First EMSO Summer School successfully conducted (T6.4) | WP6 | M18 | Summer school report available on the website. |
| MS6.1 | The EMSO academy platform operational (T6.4) | WP6 | M18 | The web application is available publicly. |
| MS2.5 | First exchanges with Directors General of other marine ERICs (MS2.5, T2.4) | WP2 | M18 | Agenda of the 2 first meetings (M9 & 18) with directors and summary of conclusions. |
| MS2.9 | Draft ToR of the Committee of National Nodes (MS2.9, T2.6) | WP2 | M19 | Draft ToR available |
| MS2.2 | 2nd Meetings with the representatives national communities on Presentations of potential models for EMSO national nodes (MS2.2, T2.2) | WP2 | M20 | Meeting Report |
| MS7.3 | Stakeholder Network Established (GEOECOMAR/MI)(T7.4) | WP7 | M24 | Catalogue of stakeholders mapped to stakeholder groups. |
| MS5.1 | Upstream services (T5.3) | WP5 | M24 | Initial implementation of upstream services |
| MS3.3 | Regional funding bodies engagement (T3.3) | WP3 / T3.3 | M24 | Report summarising outcomes with regional funding bodies engagement |
| MS2.6 | First exchanges with Directors General of other marine ERICs (MS2.6, T2.4) | WP2 | M25 | Agenda of the 2 following meetings with directors (M33 & 42) and summary of conclusions. |
| MS3.4 | Blue economy indicators - Global case studies (T3.4) | WP3 / T3.4 | M26 | Short report showcasing existing blue economy indicators usage globally |
| MS4.3 | Agreement on Augmented Regional Observation Design (T4.3) | WP3, WP2 | M28 | Deliverable D4.2 endorsed by EMSO RFs and user communities |
| MS3.5 | Workshop on Business Model Canvas - report (T3.5) | WP3 / T3.5 | M28 | Report on Outcomes of Workshop with internal stakeholders including Business Model Canvas completed. |
| MS5.2 | Involvement of Regional Facilities to upgraded e-infra (T5.1) | WP5 | M30 | Detailed information (data management to be followed) provided to Regional Facilities |
| MS2.4 | First result of the national OOS presented to the GA#2 (MS2.4, T2.3) | WP2 | M31 | Report gathering Slides presented and feedback summary |
| MS7.2 | Draft Deep-Ocean Observation Priorities Consensus Outline Agreed (IPMA)(T7.5) | WP7 | M36 | Table of contents, lead authors, and contributions matrix agreed. |
| MS6.3 | 20+ trained technical and administrative staff (T6.4) | WP6 | M36 | Training application registered trainees. |
| MS4.2 | Agreement on Protocols and Guidelines for Integration of New Sensors and Platforms (T4.2) | WP2, WP5, WP6 | M36 | Approved report (D4.3) and endorsement by WP partners. |
| MS3.6 | Review of current and prospective co-funding model scenarios (T3.5) | WP3 / T3.5 | M40 | Report summarising future funding models to consider in the final D3.4 deliverable. |
| MS2.8 | Membership engagement roadmap (V2) (MS2.8, T2.5) | WP2 | M40 | Report published |
| MS5.5 | Physical access platform (T5.6) | WP5 | M42 | Initial implementation of physical access TNA platform |
| MS5.4 | Downstream Services: catalogue (T5.5) | WP5 | M42 | Initial implementation of EMSO catalogue |
| MS5.3 | Downstream services: visualisation (T5.4) | WP5 | M42 | Initial implementation of visualisation service in EMSO.eu |
| MS4.4 | Completion of Analysis of Key Ocean Processes from Improved EMSO Instrument Design (T4.3) | WP4 (task 4.1), WP2 | M42 | Delivery and approval of report (D4.4) |
| MS7.5 | Global Deep-Ocean Observation Priorities Workshop Delivered (IPMA)(T7.4) | WP7 | M46 | Side event of the final GA (Brussels): programme, attendance list, and resolutions captured |
| MS7.4 | International Partnership Webinar Series Launched (PLOCAN)(T7.4) | WP7 | M48 | First webinar held; agenda, slides, and action log published. |
| MS4.6 | Basin-Scale Demonstration Tests Implemented (T4.5) | WP4, WP2, WP6 | M48 | Demonstration reports from three basin case studies |
| MS4.5 | EMSO Interoperability Framework Validated (T4.4) | WP4, WP5 | M48 | Draft EMSO Handbook (D4.3) validated with OceanPractices and EMSO Assembly |